SERVICE BUILDING A22,
San Michele all’Adige (TN)
Enhanced comfort and energy cost savings
Brenner highway Corporation
Energy concept, Dynamic Simulation, Execution Planning, Execution Planning for HVAC System, Consulting, Call for tenders, Load Calculation, Assistance with Construction Management: Eng. Oscar Stuffer – Solarraum srl
2009 – 2012
I – 38010 San Michele all’Adige (TN)
2.260m² 7.800m³
ClimaHouse“A”
General contractor: Collini Lavori SPA, Boller Roberto ICI Consulenti StatiC
In this project, our task was to analyze the already planned design and propose improvements. Through thorough analysis and intensive optimization, we succeeded in reducing energy consumption by 67% with only a 4% increase in costs, while simultaneously improving employee comfort. A major challenge was the glazing, for which we were able to find an excellent solution thanks to building physics calculations.